Construction Phases

Stages of the Build

 

BACK TO THE HOMEPAGE

 
Below you will find a basic timeline for the construction of EVE Park. This timeline will apply to each cluster, which are being built in order (A,B,C,D), with an estimated timeline of 4-6 weeks between each building. 
 
Phase I, Buildings A & B, are currently under construction! Both buildings now have walls, windows and a roof. Please keep an eye on your inbox for further updates on construction and occupancy notices.
 
Image (4) (1)
Construction Phase Estimated Completion Time (Days)
Excavation 45
Substructure 45
Superstructure 35
Building Envelope 50
Fit Out 90
M&E Systems Start-Up, Test & Commissioning 35
Project Closeout 75

 